Answer the following questions:
1)What is the difference between a task dependency and a task constraint?

2) Give a real-world situation when you might used the following task constraints:

  1. a) Start No Earlier Than
  2. b) Start No Later Than –
  3. c) Finish No Later Than –
  4. d) Finish No Earlier Than –
  5. e) Must Finish On –
  6. f) Must Start On –
  7. g) As Late As Possible –

3) What is the importance of a baseline?

4) What is an interim plan?

SKU: mgmt-404-review-questions Categories: ,
Share with others

Details

Answer the following questions:
1)What is the difference between a task dependency and a task constraint?

2) Give a real-world situation when you might used the following task constraints:

  1. a) Start No Earlier Than
  2. b) Start No Later Than –
  3. c) Finish No Later Than –
  4. d) Finish No Earlier Than –
  5. e) Must Finish On –
  6. f) Must Start On –
  7. g) As Late As Possible –

3) What is the importance of a baseline?

4) What is an interim plan?

Reviews

There are no reviews yet.

Only logged in customers who have purchased this product may leave a review.